Remaining Balance of Plant and Other Plant (Shared Between both Units) Remaining Balance of Plant and Other Plant (Shared Between both Units)F1

Demineralisation Station

Drawing numberRevDrawing titleScale>Paper size
HINK-A2-HY-00-GP-03002Roof Plan1:100A1
HINK-A2-HY-00-GE-00102North and South Elevations1:100A1
HINK-A2-HY-00-GE-00202East and West Elevations1:100A1
HINK-A2-HY-00-DT-00102Part Elevation Detail1:50A1

Auxiliary Boilers

Drawing numberRevDrawing titleScale>Paper size
HINK-A2-HVB-00-GA-00401Roof Plan1:100A1
HINK-A2-HVB-00-GE-00101Elevations1:100A1
HINK-A2-HVB-00-DT-00101Part Elevation Detail1:50A1

Chemical Products Storage

Drawing numberRevDrawing titleScale>Paper size
HINK-A2-HZC-00-GA-00101Roof Plan and Elevations1:100A1
HINK-A2-HZC-00-DT-00101Part Elevation Detail1:50A1

F2Sewage Treatment Plant

Drawing number RevDrawing titleScale>Paper size
HINK-A2-STP-00-GA-00102Roof Plan1:100A1
HINK-A2-STP-00-GE-02001Elevations1:100A1

Conventional Island Water Storage Tank – A

Drawing numberRevDrawing titleScale>Paper size
HINK-A2-SER-01-GA-00201Roof Plan and East Elevation1:200A1

Conventional Island Water Storage Tank – B

Drawing numberRevDrawing titleScale>Paper size
HINK-A2-SER-02-GA-00201Roof Plan and East Elevation1:200A1

Nuclear Island Water Storage Tank

Drawing numberRevDrawing titleScale>Paper size
HINK-A2-SED-00-GA-00201Roof Plan and South and East Elevations1:100A1

Degassed Water Storage Tanks/ Valve Room

Drawing numberRevDrawing titleScale>Paper size
HINK-A2-REA-00-GA-00102Plan and Elevations1:200A1

Annotations

Textual amendments

F1

Words in Sch. 1 Pt. 3 substituted (24.3.2018) by The Hinkley Point C (Nuclear Generating Station) (Amendment) Order 2018 (S.I. 2018/413), art. 1, Sch.

F2

Words in Sch. 1 Pt. 3 substituted (7.1.2022) by The Hinkley Point C (Nuclear Generating Station) (Amendment) Order 2021 (S.I. 2021/1474), arts. 1, 5(2)(3), Sch. 1