OpenLegislation

Article 9 Construction and maintenance of new or altered means of accessI1

England, Wales and Scotland

(1)

Those parts of each means of access specified in Part 1 of Schedule 4 to be constructed under this Order must be completed to the reasonable satisfaction of the highway authority and must be maintained by and at the expense of the undertaker for a period of 12 months from completion and from the expiry of that period by and at the expense of the highway authority.

(2)

Those parts of each means of access specified in Part 2 of Schedule 4 to be constructed under this Order and which are not intended to be a public highway must be completed to the reasonable satisfaction of the street authority and must be maintained by and at the expense of the undertaker for a period of 12 months from completion and from the expiry of that period by and at the expense of the street authority.

Annotations

Commencement

I1

Art. 9 in force at 14.8.2015, see art. 1