Schedule 1 AUTHORISED DEVELOPMENTI1
England, Wales and Scotland
In the County Borough of Rhondda Cynon Taf—
A nationally significant infrastructure project as defined in sections 14(1)(a) and 15 of the 2008 Act consisting of a generating station with a gross rated electrical output of up to 299MWe comprising—
Numbered work 1 development comprising the demolition of all existing buildings and structures, including foundations, hardstanding and services,
Numbered work 2A development comprising—
- (a)
up to 5 gas turbine generators; and
- (b)
up to 5 exhaust gas emission flue stacks,
- (a)
Numbered work 2B development comprising—
- (a)
an administration building;
- (b)
a store;
- (c)
a control room/office/workshop;
- (d)
telemetry apparatus;
- (e)
F1three black start diesel generators where one gas turbine generator is constructed and one black start diesel generator where two, three, four or five gas turbine generators are constructed;
- (f)
a natural gas receiving station and gas treatment compound containing—
- (i)
a pipeline inspection gauge (PIG) receiving facility;
- (ii)
isolation valves, metering, heating, filtering, compression, pressure regulation equipment;
- (iii)
electricity supply kiosk; and
- (iv)
control and instrumentation kiosks,
- (i)
- (g)
F2external fin fan cooler (where only one gas turbine generator is constructed).
- (a)
Numbered work 2C development comprising a switchyard / banking compound containing up to eight transformers, switchgear building and other plant required to manage the transmission of electricity,
Numbered work 2D development comprising a construction and maintenance compound including new hardstanding,
Numbered work 2E development comprising—
- (a)
security infrastructure, including cameras, perimeter fencing and a gatehouse;
- (b)
site lighting infrastructure, including perimeter lighting columns;
- (c)
internal roadways, car parking, pedestrian network, cycle parking, hardstanding and water treatment trailers;
- (d)
site drainage, attenuation pond and waste management infrastructure;
- (e)
electricity, water, wastewater and telecommunications and other services;
- (f)
a raw / fire water tank and demineralised water storage tank;
- (g)
landscaping including tree planting, fencing and other boundary treatments and ecological mitigation (including bat mitigation structure);
- (h)
tree and hedge removal;
- (i)
high voltage and low voltage cabling, equipment and controls and associated telemetry and electrical protection auxiliary cabling;
- (j)
underground gas pipeline connection, associated telemetry and cathodic protection test / transformer rectifier unit; and
- (k)
other ancillary equipment,
- (a)
Numbered work 2F development comprising new or modified permanent means of access to numbered work 2 including permanent road surface, drainage, gates and fencing,
Numbered work 2G development comprising the maintenance strengthening or re-laying in a new location of the existing culvert forming that part of ordinary watercourse River Camnant within the Order limits, such works subject to maintaining the existing flow rate.
Annotations
Textual amendments
- F1
Words in Sch. 1 substituted (12.11.2016) by The Hirwaun Generating Station (Amendment) Order 2016 (S.I. 2016/1087), arts. 1, 5(2)
- F2
Words in Sch. 1 inserted (12.11.2016) by The Hirwaun Generating Station (Amendment) Order 2016 (S.I. 2016/1087), arts. 1, 5(3)
Commencement
- I1
Sch. 1 in force at 14.8.2015, see art. 1