F1(1)

No numbered work of the authorised development is to commence other than the bat mitigation structure forming part of numbered work 2E(g) of the authorised development until a construction environment management plan covering that numbered work has been submitted to and approved by the relevant planning authority.

(2)

All construction works must be undertaken in accordance with the approved construction environment management plan.

Annotations

Textual amendments

F1

Sch. 2 para. 12(1) substituted (20.10.2017) by The Hirwaun Generating Station (Amendment) Order 2017 (S.I. 2017/1009), arts. 1, 2(12)

Commencement

I1

Sch. 2 para. 12 in force at 14.8.2015, see art. 1