OpenLegislation

Article 11 Closure and diversion of public rights of way and access landI1

England, Wales and Scotland

(1)

The undertaker may, in connection with the carrying out of the authorised project—

(a)

temporarily close each of the public rights of way specified in column (1) of Part 1 of Schedule 4 (public rights of way to be closed or diverted and access land) to the extent specified in column (2), by reference to the numbers and letters shown on the public rights of way plan;

(b)

permanently divert each of the public rights of way specified in column (1) of Part 2 Schedule 4 (public rights of way to be closed or diverted and access land) to the extent specified, in column (2) of that Schedule;

(c)

provide the substitute public rights of way to those diverted as described in column (3) of Part 2 of Schedule 4 (public rights of way to be closed or diverted and access land) between the specified terminus points;

(d)

temporarily divert each of the public rights of way specified in column (1) of Part 3 F1of Schedule 4 (public rights of way to be closed or diverted and access land) to the extent specified, in column (2) of that Schedule;

(e)

provide the substitute public rights of way to those temporarily diverted for the duration of that diversion as described in column (3) of Part 3 of Schedule 4 (public rights of way to be closed or diverted and access land) between the specified terminus points; and

(f)

temporarily close, prohibit the use of or restrict the use of the access land specified in column (1) of Part 4 of Schedule 4 (public rights of way to be closed or diverted and access land) to the extent specified in column (2), by reference to the area shown on the public rights of way plan.

(2)

The rights of access conferred by section 2 of the 2000 Act (rights of the public in relation to access land) are suspended in relation to any access land specified in column (1) of Part 4 of Schedule 4 (public rights of way to be closed or diverted and access land) to the extent specified in column (2), by reference to the area shown on the public rights of way plan.

(3)

The period of suspension under paragraph (2) lasts for the period of the temporary closure.

Annotations

Textual amendments

F1

Word in art. 11(1)(d) inserted (31.1.2024) by The Hornsea Four Offshore Wind Farm (Correction) Order 2024 (S.I. 2024/117), art. 1(2), Sch.

Commencement

I1

Art. 11 in force at 3.8.2023, see art. 1

Notes on the whole SI

Textual amendments

F1

Word in preamble substituted (31.1.2024) by The Hornsea Four Offshore Wind Farm (Correction) Order 2024 (S.I. 2024/117), art. 1(2), Sch.