Article 3 Development consent etc. granted by this OrderI1
England, Wales and Scotland
Subject to the provisions of this Order and to the requirements, the undertaker is granted—
development consent for the authorised development; and
consent for the ancillary works,
to be carried out within the Order limits.
Work Nos. 1 to 5 (save for those elements of Work No. 5(a) located landward of MHWS in order to connect to Work No. 6) must be constructed within the Order limits seaward of MHWS and Work Nos. 6 to 10 (save for those elements of Work Nos. 9(a) and 9(d) located seaward of MHWS for foreshore access) must be constructed within the Order limits landward of MHWS.
Annotations
Commencement
- I1
Art. 3 in force at 3.8.2023, see art. 1
Notes on the whole SI
Textual amendments
- F1
Word in preamble substituted (31.1.2024) by The Hornsea Four Offshore Wind Farm (Correction) Order 2024 (S.I. 2024/117), art. 1(2), Sch.