Paragraph 16 Surface waterI1
England, Wales and Scotland
No stage of the connection works in Work No. 7 may commence until, in respect of that installation, a detailed surface water scheme has been prepared in consultation with the relevant sewerage and drainage authorities and the Environment Agency and submitted to and approved by the lead local flood authority.
The detailed surface water schemes must accord with the outline onshore infrastructure drainage strategy and—
be based on sustainable drainage principles;
include an assessment of the hydrological and hydrogeological context of the connection works in Work No. 7; and
include detailed designs of a surface water drainage scheme.
Construction of the connection works in Work No. 7 must be carried out in accordance with the approved scheme.
Annotations
Commencement
- I1
Sch. 1 Pt. 3 para. 16 in force at 3.8.2023, see art. 1
Notes on the whole SI
Textual amendments
- F1
Word in preamble substituted (31.1.2024) by The Hornsea Four Offshore Wind Farm (Correction) Order 2024 (S.I. 2024/117), art. 1(2), Sch.