OpenLegislation

Paragraph 18 Code of construction practiceI1

England, Wales and Scotland

(1)

No stage of the connection works, Work No. 2 (f) or Work No. 5 may commence until a code of construction practice (which must accord with the outline code of construction practice but may not include the outline construction traffic management plan in the event that the outline construction traffic management plan has been, or is in the process of being, approved separately pursuant to requirement 19) for that stage of the connection works has been submitted to and approved by the relevant planning authority, in consultation with the Environment Agency, the relevant SNCBs and, if applicable, the MMO.

(2)

All connection works must be undertaken in accordance with the relevant approved code of construction practice.

Annotations

Commencement

I1

Sch. 1 Pt. 3 para. 18 in force at 3.8.2023, see art. 1

Notes on the whole SI

Textual amendments

F1

Word in preamble substituted (31.1.2024) by The Hornsea Four Offshore Wind Farm (Correction) Order 2024 (S.I. 2024/117), art. 1(2), Sch.