Paragraph 7 Co-operation during constructionI1
England, Wales and Scotland
Insofar as the construction of the Hornsea Four authorised development is or may be undertaken concurrently with the Dogger Bank authorised development, the undertaker shall—
co-operate with Dogger Bank with a view to ensuring—
the co-ordination of construction programming and the carrying out of works; and
that access for the purposes of constructing the respective authorised developments is maintained for the undertaker and Dogger Bank and their respective contractors.
use reasonable endeavours to avoid any conflict arising between the carrying out of the respective authorised developments.