OpenLegislation

Paragraph 16 Onshore ArchaeologyI1

England and Wales

(1)

No phase of the connection works may commence until for that phase a written scheme of archaeological investigation (which must accord with the outline onshore written scheme of investigation) for Work Nos. 6 to 15 has been submitted to and approved by the relevant planning authority in consultation with Norfolk County Council and the Historic Buildings and Monuments Commission for England.

(2)

The term “commence” as used in requirement 16(1) shall include any onshore site preparation works.

(3)

Any archaeological investigations must be carried out in accordance with the approved scheme.

(4)

The archaeological site investigations and post investigation assessment must be completed for that phase in accordance with the programme set out in the written scheme of archaeological investigation and provision made for analysis, publication and dissemination of results and archive deposition secured for that phase.

Annotations

Commencement

I1

Sch. 1 Pt. 3 para. 16 in force at 22.1.2021, see art. 1

Notes on the whole SI

Textual amendments

F1

Preamble: bracket omitted (21.5.2021) by virtue of The Hornsea Three Offshore Wind Farm (Correction) Order 2021 (S.I. 2021/599), art. 1(2), Sch.