Paragraph 6 Phases of authorised developmentI1

England and Wales

(1)

The authorised development may not be commenced until a written scheme setting out the phases of construction of the authorised project has been submitted to and approved by the relevant planning authority, in relation to the connection works, or the MMO, in relation to works seaward of MHWS.

(2)

The phases of construction referred to in sub-paragraph (1) shall not exceed two, save that each phase may be undertaken in any number of stages as prescribed in the written scheme.

(3)

The scheme must be implemented as approved.

Annotations

Commencement

I1

Sch. 1 Pt. 3 para. 6 in force at 22.1.2021, see art. 1

Notes on the whole SI

Textual amendments

F1

Preamble: bracket omitted (21.5.2021) by virtue of The Hornsea Three Offshore Wind Farm (Correction) Order 2021 (S.I. 2021/599), art. 1(2), Sch.