OpenLegislation

Paragraph 23 Reporting of cable protectionI1

England and Wales

(1)

Not more than 4 months following completion of the construction phase of the project, the undertaker shall provide the MMO and the relevant SNCBs with a report setting out details of the cable protection used for the authorised scheme.

(2)

The report shall include the following information—

(a)

location of the cable protection;

(b)

volume of cable protection; and

(c)

any other information relating to the cable protection as agreed between the MMO and the undertaker.

Annotations

Commencement

I1

Sch. 11 Pt. 2 para. 23 in force at 22.1.2021, see art. 1

Notes on the whole SI

Textual amendments

F1

Preamble: bracket omitted (21.5.2021) by virtue of The Hornsea Three Offshore Wind Farm (Correction) Order 2021 (S.I. 2021/599), art. 1(2), Sch.