Paragraph 15 I1

England and Wales

(1)

Each programme, statement, plan, protocol or scheme required to be approved under condition 14 (save for that required under condition 14(1)(f)) must be submitted for approval at least four months prior to the intended commencement of licensed activities, except where otherwise stated or unless otherwise agreed in writing by the MMO.

(2)

The pre-construction monitoring surveys, construction monitoring, post-construction monitoring and related reporting required under condition 14(1)(f) must be submitted in accordance with the following, unless otherwise agreed in writing with the MMO—

(a)

at least four months prior to the first survey, detail of any pre–construction surveys and an outline of all proposed monitoring;

(b)

at least four months prior to construction, detail on construction monitoring; and

(c)

at least four months prior to commissioning, detail of post-construction (and operational) monitoring.

(3)

The design plan required by condition 14(1)(a) shall be prepared by the undertaker and determined by the MMO in accordance with the Development Principles.

(4)

The MMO shall determine an application for consent made under this article within a period of four months commencing on the date the application is received by the MMO, unless otherwise agreed in writing with the undertaker.

(5)

The licensed activities must be carried out in accordance with the approved plans, protocols, statements, schemes and details approved under condition 14, unless otherwise agreed in writing by the MMO.

Annotations

Commencement

I1

Sch. 12 Pt. 2 para. 15 in force at 22.1.2021, see art. 1