Paragraph 3 I1

England and Wales

(1)

The total length of the cables and the volume of their cable protection (excluding cable crossings) must not exceed the following—

WorkLengthCable protection
Work Nos. 2 and 31,371 kilometres1,371,000 cubic metres
Work No. 53 kilometresNone
(2)

No cable protection by way of concrete mattresses may be used in European Sites or MCZ.

(3)

No more than 6% of the length of the cables in Work Nos. 2, 3 and 5 falling within any European Site shall be subject to cable protection.

(4)

No more than 7% of the length of the cables in Works Nos. 2, 3 and 5 falling within any MCZ shall be subject to cable protection.

Annotations

Commencement

I1

Sch. 12 Pt. 2 para. 3 in force at 22.1.2021, see art. 1

Notes on the whole SI

Textual amendments

F1

Preamble: bracket omitted (21.5.2021) by virtue of The Hornsea Three Offshore Wind Farm (Correction) Order 2021 (S.I. 2021/599), art. 1(2), Sch.