Paragraph 3 I1
England and Wales
(1)
The total length of the cables and the volume of their cable protection (excluding cable crossings) must not exceed the following—
| Work | Length | Cable protection |
|---|---|---|
| Work Nos. 2 and 3 | 1,371 kilometres | 1,371,000 cubic metres |
| Work No. 5 | 3 kilometres | None |
(2)
No cable protection by way of concrete mattresses may be used in European Sites or MCZ.
(3)
No more than 6% of the length of the cables in Work Nos. 2, 3 and 5 falling within any European Site shall be subject to cable protection.
(4)
No more than 7% of the length of the cables in Works Nos. 2, 3 and 5 falling within any MCZ shall be subject to cable protection.