Paragraph 5 Phases of authorised developmentI1
England and Wales
(1)
The authorised development may not be commenced until a written scheme setting out the phases of construction of the authorised project has been submitted to and approved by the MMO.
(2)
The phases of construction referred to in paragraph (1) shall not exceed two, save that each phase may be undertaken in any number of stages as prescribed in the written scheme.
(3)
The scheme must be implemented as approved.