Paragraph 10 I1
England and Wales
The authorised development may not be commenced until a plan for the work of a Steering Group who will shape and inform the scope and delivery of Sandbanks Implementation Plans for the NNSSR and the WNNC (“the SIPs”) has been submitted to and approved by the Secretary of State. Such plan to include:
terms of reference of the Steering Group;
the membership of the Steering Group;
the schedule of meetings, timetable for preparation of the SIPs and reporting and review periods; and
the dispute resolution mechanism.
Annotations
Commencement
- I1
Sch. 14 para. 10 in force at 22.1.2021, see art. 1
Notes on the whole SI
Textual amendments
- F1
Preamble: bracket omitted (21.5.2021) by virtue of The Hornsea Three Offshore Wind Farm (Correction) Order 2021 (S.I. 2021/599), art. 1(2), Sch.