OpenLegislation

Paragraph 2 I1

England and Wales

The authorised development may not be commenced until a plan for the work of the Offshore Ornithology Engagement Group (“OOEG”) has been submitted to and approved by the Secretary of State. Such plan to include:

(a)

terms of Reference of the OOEG;

(b)

details of the membership of the OOEG;

(c)

details of the schedule of meetings, timetable for preparation of the kittiwake implementation and monitoring plan (the “KIMP”) and reporting and review periods; and

(d)

the dispute resolution mechanism.

Annotations

Commencement

I1

Sch. 14 para. 2 in force at 22.1.2021, see art. 1

Notes on the whole SI

Textual amendments

F1

Preamble: bracket omitted (21.5.2021) by virtue of The Hornsea Three Offshore Wind Farm (Correction) Order 2021 (S.I. 2021/599), art. 1(2), Sch.