OpenLegislation

Paragraph 4 F1

England and Wales

The undertaker must implement the measures as set out in the KIMP approved by the Secretary of State and no operation of any turbine forming part of the authorised development may be commenced until three full breeding seasons have elapsed from the implementation of three of the artificial nest structures and no final commissioning of the authorised development must take place until the fourth artificial nest structure has been implemented For the purposes of this paragraph each breeding season is assumed to have commenced on 1 March in each year and ended on 30 September.

Annotations

Textual amendments

F1

Sch. 14 para. 4 substituted (10.5.2024) by The Hornsea Three Offshore Wind Farm (Amendment) Order 2024 (S.I. 2024/627), arts. 1, 3(b)

Notes on the whole SI

Textual amendments

F1

Preamble: bracket omitted (21.5.2021) by virtue of The Hornsea Three Offshore Wind Farm (Correction) Order 2021 (S.I. 2021/599), art. 1(2), Sch.