Article 12 Access to worksI1
England, Wales and Scotland
The undertaker may for the purposes of the authorised project—
form and lay out means of access, or improve existing means of access, in the locations set out in column (2) of Schedule 4 (access to works); and
with the approval of the local planning authority after consultation with the highway authority, form and lay out such other means of access, or improve existing means of access, at such locations within the Order limits, as the undertaker reasonably requires for the purposes of the authorised project.
If the local planning authority fails to notify the undertaker of its decision within 28 days of receiving an application for approval under paragraph (1)(b), the local planning authority is deemed to have given approval.