Paragraph 6 Ecological management plan landward of mean low water springsI1

England, Wales and Scotland

(1)

No part of the authorised development landward of MLWS may be commenced within the area of a local planning authority until F1an ecological management plan relating to the land landward of MLWS based on the outline ecological management plan and reflecting the survey results and ecological mitigation measures included in the environmental statement has been submitted to and approved by the local planning authority in consultation with Natural England, the Environment Agency and, to the extent that the plan relates to the intertidal area, the MMO.

(2)

The ecological management plan must include an implementation timetable and must be carried out as approved.

(3)

The ecological management plan must be submitted for approval at least 4 months before the intended start of construction unless otherwise agreed by the local planning authority in consultation with Natural England.

Annotations

Textual amendments

F1

Words in Sch. 1 Pt. 3 para. 6(1) substituted (17.11.2016) by The Hornsea Two Offshore Wind Farm (Correction) Order 2016 (S.I. 2016/1104), art. 1(2), Sch.

Commencement

I1

Sch. 1 para. 6 in force at 7.9.2016, see art. 1(2)