Paragraph 10 Pre-construction plans and documentationI1

England, Wales and Scotland

(1)

Each programme, statement, plan, protocol or scheme required to be approved under Condition 8—

(a)

must be submitted for approval at least 4 months before the intended start of construction, except where otherwise stated or where an alternative date is agreed in writing by the MMO; and

(b)

must be accompanied by—

(i)

a statement confirming that the undertaker has complied with Condition 8(3) in relation to the programme, statement, plan, protocol or scheme; and

(ii)

any comments received by the undertaker from the other undertakers, or a statement from the undertaker confirming that no such comments were received.

(2)

The undertaker must comply with the plans and documentation approved under Condition 8 in carrying out the licensed activities unless otherwise agreed in writing by the MMO.

(3)

Before agreeing an alternative date under paragraph (1)(a) or a change to approved details under paragraph (2) relating to any document in respect of which consultation is required under Condition 8, the MMO must consult the relevant consultation body referred to in that Condition.