Paragraph 3 I1
England, Wales and Scotland
The undertaker must not under the powers of this Order acquire—
(a)
new rights over the C.GEN relevant land; or
(b)
new rights over the thermal buffer zone, except for the purposes of access and maintenance; or
(c)
new rights over crossing zones,
without the consent of C.GEN, such consent not to be unreasonably withheld or delayed but which may be given subject to reasonable conditions.