Paragraph 8 I1

England, Wales and Scotland

The undertaker must give to the relevant Hornsea One company not less than 28 days’ written notice of its intention to commence the construction of the specified works and, not more than 28 days after completion of their construction, must give the relevant Hornsea One company written notice of the completion.

Annotations

Commencement

I1

Sch. 12 Pt. 12 para. 8 in force at 7.9.2016, see art. 1(2)