Section 152 Approval condition where development order grants permission for buildingI1

Changes not yet applied. Later legislation changes this provision in ways not yet written into the text below:

(1)

In section 60 of the Town and Country Planning Act 1990 (permission granted by development order), after subsection (1) insert—

“(1A)

Without prejudice to the generality of subsection (1), where planning permission is granted by a development order for building operations in England, the order may require the approval of the local planning authority, or the Secretary of State, to be obtained—

(a)

for those operations, or

(b)

with respect to any matters that relate to those operations, or to the use of the land in question following those operations, and are specified in the order.”

I2(2)

In subsection (2) of that section, after “any buildings” insert “ in Wales ”.

(3)

In subsection (2B) of that section, for “subsection (1)” substitute “ subsections (1) and (1A) ”.

(4)

In section 70A of that Act (power to decline to determine subsequent application), in subsection (5)(b), for “section 60(2)” substitute “ section 60(1A), (2) ”.

Annotations

Commencement

I1

S. 152(1) in force at Royal Assent see s. 152(1)(d)

I2

S. 152(2)-(4) in force at 13.7.2016 by S.I. 2016/733, reg. 3(e)

Notes on Part 6

Modifications

C1

Pts. 6, 7: power to amend conferred (26.12.2023) by Levelling-up and Regeneration Act 2023 (c. 55), ss. 132, 255(3)(a) (with s. 247)