Paragraph 10 Surface water drainageI1
England and Wales
No part of the authorised development may commence, save for the permitted preliminary works, until details of the temporary surface water drainage systems, including means of pollution control in accordance with the construction environmental management plan submitted pursuant to requirement 14 and a management and maintenance plan to ensure that the systems remain fully operational throughout the construction of the relevant part of the authorised development have, for that part, been submitted to, and after consultation with the lead local flood authority and North East Lindsey Internal Drainage Board, approved by the relevant planning authority.
The scheme approved pursuant to sub-paragraph (1) must be implemented as approved and maintained throughout the construction of the authorised development unless otherwise agreed with the relevant planning authority.
Details of the permanent surface water drainage systems, including a programme for their implementation, must be submitted to, and after consultation with the Environment Agency, the lead local flood authority, Anglian Water and North East Lindsey Internal Drainage Board, approved by the relevant planning authority prior to the start of construction of any part of those systems.
The details submitted and approved pursuant to sub-paragraphs (1) and (3) of this requirement must be in accordance with the principles set out in chapter 12 (surface water, flood risk and drainage) of the environmental statement and the flood risk assessment.
The scheme approved pursuant to sub-paragraph (3) must be implemented as approved and maintained throughout the operation of the authorised development unless otherwise agreed with the relevant planning authority.
Annotations
Commencement
- I1
Sch. 2 para. 10 in force at 1.9.2020, see art. 1