Paragraph 4 Notice of date of final commissioningI1

England and Wales

Notice of the intended date of final commissioning of the authorised development must be given to the relevant planning authority where practicable prior to such date of final commissioning and in any event within seven days from the date of final commissioning.

Annotations

Commencement

I1

Sch. 2 para. 4 in force at 1.9.2020, see art. 1