Before commencing any part of the authorised development which would have an effect on the operation or maintenance of the pipeline and access to it, the undertaker must submit to CLH plans and sections of the proposed works and such further particulars as CLH may, within 28 days from the day on which plans and sections are submitted under this paragraph, reasonably require.