Paragraph 181 I1

England and Wales

Work in relation to which an estimate is submitted must not be commenced by Northern Powergrid until that estimate is agreed with the undertaker in writing and a purchase order up to the value of the approved estimate has been issued by the undertaker to Northern Powergrid and an easement for the routes of the apparatus has been granted to Northern Powergrid under paragraph 173(1) for the benefit of its statutory undertaking.

Annotations

Commencement

I1

Sch. 9 para. 181 in force at 1.9.2020, see art. 1