Paragraph 36 Authorisation of works details affecting pipelines or protected crossingsI1

England and Wales

(1)

Before commencing any part of a relevant work the undertaker must submit the works details to P66 in accordance with paragraph 103.

(2)

The works details submitted under sub-paragraph (1) will be treated as having been received by P66 on the date—

(a)

that the undertaker obtains written acknowledgement of receipt from P66; or

(b)

two clear working days following the date that the work details were submitted under sub-paragraph (1),

whichever is earliest.

(3)

The undertaker must as soon as reasonably practicable provide such further particulars as P66 may, within 60 days from the receipt of the works details under sub-paragraph (2), reasonably require.

Annotations

Commencement

I1

Sch. 9 para. 36 in force at 1.9.2020, see art. 1