England and Wales

Before carrying out a relevant work the undertaker must—

(a)

provide P66 with baseline data for any existing cathodic protection of the affected asset; and

(b)

carry out a pipeline settlement and stress analysis to demonstrate any potential pipeline movement will not present an integrity risk to the affected asset.