Paragraph 41 Further provisions about relevant worksI1
England and Wales
Before carrying out a relevant work the undertaker must—
(a)
provide P66 with baseline data for any existing cathodic protection of the affected asset; and
(b)
carry out a pipeline settlement and stress analysis to demonstrate any potential pipeline movement will not present an integrity risk to the affected asset.
Annotations
Commencement
- I1
Sch. 9 para. 41 in force at 1.9.2020, see art. 1