Regulation 35 Notice of decisions on an application in relation to WalesI1
England and Wales
This regulation applies in relation to decisions on an application for development in Wales.
In addition to the persons listed in section 60(2) of the 2024 Act, the Welsh Ministers must notify the persons listed in paragraph 1 of Schedule 2 of their decision to either make an infrastructure consent order or refuse infrastructure consent.
In addition to the persons listed in section 60(4) of the 2024 Act, the examining authority must notify the persons listed in paragraph 1 of Schedule 2 of their decision either that an infrastructure consent order is to be made or to refuse infrastructure consent.
Where an application includes a request to authorise the compulsory acquisition of land, or of an interest in or right over land, see also regulation 26(2) of the 2025 Compulsory Acquisition Regulations for additional requirements as to notice of decisions.