Regulation 6 Duration of order granting development consentI1
England, Wales and Scotland
Development for which development consent is granted must be begun before the end of a period of five years beginning on the date on which the order granting development consent is made.
Where an order granting development consent authorises the compulsory acquisition of land, and a notice to treat is served under section 5 of the Compulsory Purchase Act 1965f1 or in Scotland under section 17 of the Lands Clauses Consolidation (Scotland) Act 1845f2, that notice must be served before the end of a period of five years beginning on the date on which the order granting development consent is made.
Annotations
Commencement
Footnotes
- f1
-
1965 c.56. Section 5 was amended by section 67 of the Planning and Compensation Act 1991 (c.34) and by S.I. 2009/1307.
- f2