OpenLegislation

Paragraph 24 Lights on tidal works etc. during construction

Original text. Later amendments are not shown.

The undertaker shall at or near—

(a)

a tidal work, including any temporary work; or

(b)

any plant, equipment or other obstruction placed, in connection with any authorised development or any work authorised by article 7 (subsidiary works), within the area of seaward construction activity,

during the whole time of the construction, reconstruction, extension, enlargement, replacement or relaying, exhibit every night from sunset to sunrise such lights, if any, and take such other steps for the prevention of danger to navigation as the Secretary of State [and the conservancy authority if applicable or, failing agreement between them, the Secretary of State] may from time to time direct.