Paragraph 15 Contaminated land and groundwater
No [stage of the] authorised development shall commence until a written scheme [applicable to that stage,] to deal with the contamination of any land, including groundwater, within the Order limits which is likely to cause significant harm to persons or pollution of controlled waters or the environment has, after consultation with the relevant planning authority and the Environment Agency, been submitted to and approved by the Commission.
The scheme shall include an investigation and assessment report, prepared by a specialist consultant approved by the relevant planning authority, to identify the extent of any contamination and the remedial measures to be taken to render the land fit for its intended purpose, together with a management plan which sets out long-term measures with respect to any contaminants remaining on the site.
Remediation must be carried out in accordance with the approved scheme.