Section 12 Dams and reservoirsI1
England and Wales
The following kinds of development are significant infrastructure projects—
(a)
the construction of a dam or reservoir in Wales if the volume of water to be held back by the dam or stored in the reservoir is expected to exceed 10 million cubic metres;
(b)
the alteration of a dam or reservoir in Wales if the additional volume of water to be held back by the dam or stored in the reservoir as a result of the alteration is expected to exceed 10 million cubic metres.
Annotations
Commencement
- I1
S. 12 in force at 4.6.2024, see s. 147(1)(a)