OpenLegislation

Paragraph 10 Construction hours

Original text. Later amendments are not shown.

(1)

Subject to sub-paragraph (2), no construction works are to take place except between—

(a)

07:00 and 19:00 Monday to Friday; and

(b)

07:00 and 16:00 on Saturdays, Sundays and public holidays,

unless otherwise agreed by the relevant planning authority.

(2)

Emergency works are permitted outside the hours referred to in sub-paragraph (1).

(3)

Any emergency works carried out under sub-paragraph (2) must be notified to the relevant planning authority within 72 hours of their commencement.