Work No.1A–An underground gas storage cavity at GR, E370280.37, N369293.28 of up to 100m diameter by up to 130m deep formed by solution mining within a depth range of 450m and 850m below ground level with a maximum drilling depth of no more than 33m below the bottom of the 30 feet marls formation identified in the seismic survey report.

Work No.1B–An underground gas storage cavity at GR, E370787.74, N369459.53 of up to 100m diameter by up to130m deep formed by solution mining within a depth range of 450m and 850m below ground level with a maximum drilling depth of no more than 33m below the bottom of the 30 feet marls formation identified in the seismic survey report.

Work No.1C–An underground gas storage cavity at GR E371332.02, N369744.22 of up to 100m diameter by up to 130m deep formed by solution mining within a depth range of 450m and 850m below ground level with a maximum drilling depth of no more than 33m below the bottom of the 30 feet marls formation identified in the seismic survey report.

Work No.1D–An underground gas storage cavity at GR E370832.07, N369022.17 of up to 100m diameter by up to 130m deep formed by solution mining within a depth range of 450m and 850m below ground level with a maximum drilling depth of no more than 33m below the bottom of the 30 feet marls formation identified in the seismic survey report.

Work No.1E–An underground gas storage cavity at GR, E371002.50, N369237.99 of up to 100m diameter by up to 130m deep formed by solution mining within a depth range of 450m and 850m below ground level with a maximum drilling depth of no more than 33m below the bottom of the 30 feet marls formation identified in the seismic survey report.

Work No.1F–An underground gas storage cavity at GR E371300.15, N369287.26 of up to 100m diameter by up to 130m deep formed by solution mining within a depth range of 450m and 850m below ground level with a maximum drilling depth of no more than 33m below the bottom of the 30 feet marls formation identified in the seismic survey report.

Work No.1G–An underground gas storage cavity at GR E371103.31, N368976.85 of up to 100m diameter by up to 130m deep formed by solution mining within a depth range of 450m and 850m below ground level with a maximum drilling depth of no more than 33m below the bottom of the 30 feet marls formation identified in the seismic survey report.

Work No.1H–An underground gas storage cavity at GR, E370195.52, N370206.82 of up to 100m diameter by up to130m deep formed by solution mining within a depth range of 450m and 850m below ground level with a maximum drilling depth of no more than 33m below the bottom of the 30 feet marls formation identified in the seismic survey report.

Work No.1J–An underground gas storage cavity at GR E371075.22, N370242.38 of up to 100m diameter by up to 130m deep formed by solution mining within a depth range of 450m and 850m below ground level with a maximum drilling depth of no more than 33m below the bottom of the 30 feet marls formation identified in the seismic survey report.

Work No.1K–An underground gas storage cavity at GR E370590.41, N369240.06 of up to 100m diameter by up to 130m deep formed by solution mining within a depth range of 450m and 850m below ground level with a maximum drilling depth of no more than 33m below the bottom of the 30 feet marls formation identified in the seismic survey report.

Work No.1L–An underground gas storage cavity at GR E370978.36, N370499.76 of up to 100m diameter by up to 130m deep formed by solution mining within a depth range of 450m and 850m below ground level with a maximum drilling depth of no more than 33m below the bottom of the 30 feet marls formation identified in the seismic survey report.

Work No.1M–An underground gas storage cavity at GR E370914.66, N368757.87 of up to 100m diameter by up to 130m deep formed by solution mining within a depth range of 450m and 850m below ground level with a maximum drilling depth of no more than 33m below the bottom of the 30 feet marls formation identified in the seismic survey report.

Work No.1N–An underground gas storage cavity at GR E371186.66, N368630.79 of up to 100m diameter by up to 130m deep formed by solution mining within a depth range of 450m and 850m below ground level with a maximum drilling depth of no more than 33m below the bottom of the 30 feet marls formation identified in the seismic survey report.

Work No.1P–An underground gas storage cavity at GR E371368.25, N368892.81, of up to 100m diameter by up to 130m deep formed by solution mining within a depth range of 450m and 850m below ground level with a maximum drilling depth of no more than 33m below the bottom of the 30 feet marls formation identified in the seismic survey report.

Work No.1Q–An underground gas storage cavity at GR E371605.04, N369035.91, of up to 100m diameter by up to 130m deep formed by solution mining within a depth range of 450m and 850m below ground level with a maximum drilling depth of no more than 33m below the bottom of the 30 feet marls formation identified in the seismic survey report.

Work No.1R–An underground gas storage cavity at GR, E371578.01, N369311.02 of up to 100m diameter by up to 130m deep formed by solution mining within a depth range of 450m and 850m below ground level with a maximum drilling depth of no more than 33m below the bottom of the 30 feet marls formation identified in the seismic survey report.

Work No.1S–An underground gas storage cavity at GR E371574.94, N369612.17 of up to 100m diameter by up to 130m deep formed by solution mining within a depth range of 450m and 850m below ground level with a maximum drilling depth of no more than 33m below the bottom of the 30 feet marls formation identified in the seismic survey report.

Work No.1T–An underground gas storage cavity at GR E371749.84, N369855.91 of up to 100m diameter by up to 130m deep formed by solution mining within a depth range of 450m and 850m below ground level with a maximum drilling depth of no more than 33m below the bottom of the 30 feet marls formation identified in the seismic survey report.

Work No.1U–An underground gas storage cavity at GR E372023.83, N369978.09 of up to 100m diameter by up to 130m deep formed by solution mining within a depth range of 450m and 850m below ground level with a maximum drilling depth of no more than 33m below the bottom of the 30 feet marls formation identified in the seismic survey report.

Notes on Schedule 1

Commencement

I1

Sch. 1 in force at 5.4.2017, see art. 1