Paragraph 27 I1
England and Wales
The undertaker must before commencing construction of any specified work or carrying out any works on Canal & River Trust property whatsoever supply to the Canal & River Trust proper and sufficient plans of that work and such further particulars available to it as the Canal & River Trust may within 14 days of the submission of the plans reasonably require for the reasonable approval (having regard to the undertaker’s timetable for the construction of the authorised development) of the engineer and the specified work must not be commenced without such approval except in accordance with article 40 (arbitration).
If–
at the expiry of the period of 28 days beginning on the date on which plans (and any other particulars reasonably required under sub-paragraph (1)) have been submitted to the Canal & River Trust for its consent under sub-paragraph (1); and
the engineer has not served
notice of refusal of those plans; and
the grounds for refusal upon of those plans,
the undertaker may serve upon the engineer a determination notice.
If–
the undertaker has served a determination notice referred to in paragraph 27(2) and the period of 14 days from the date of service has expired; and
the engineer has not served upon the undertaker;
notice of refusal of those plans; and
the grounds of refusal,
the engineer is deemed to have approved the plans as submitted.
If by the end of the period of 28 days beginning with the date on which written notice was served upon the engineer under paragraph 27(2), the Canal & River Trust gives notice to the undertaker that the Canal & River Trust desires itself to construct any part of a specified work which in the opinion of the engineer may or will cause any detriment in respect of Canal & River Trust property or the safe operation of any waterway, then if the undertaker requires such part of such specified work to be constructed the Canal & River Trust must construct it with all reasonable dispatch on behalf of and to the reasonable satisfaction of the undertaker in accordance with the plans approved or deemed to be approved or settled under this paragraph, and under the supervision of the undertaker.
When signifying his approval of the plans, the engineer may specify any protective works (whether temporary or permanent) which in his opinion should be carried out before commencement of the construction of a specified work to prevent any detriment and such protective works (which for the avoidance of doubt may include requirements to fence any proposed works in order to separate the same from the waterways, ponds or watercourses situated on the Canal & River Trust property either on a permanent or temporary basis) as may be reasonably necessary to prevent detriment must be constructed by the undertaker, as agreed between the parties or settled by arbitration in accordance with article 40 (arbitration) and such protective works must be carried out at the expense of the undertaker with all reasonable dispatch and the undertaker must not commence the construction of the specified works until the engineer has notified the undertaker that the protective works have been completed to his reasonable satisfaction.
The undertaker shall pay to the Canal & River Trust a capitalised sum representing the reasonably increased or additional cost of maintaining and, when necessary, renewing any works, including any permanent protective works provided under sub-paragraph (5) above, and of carrying out any additional dredging of the waterway reasonably necessitated by the exercise of any of the powers under this Order but if the cost of maintaining the waterway, or of works of renewals of the waterway, is reduced in consequence of any such works, a capitalised sum representing such reasonable saving shall be set off against any sum payable by the undertaker to the Canal & River Trust under this paragraph.
In the event that the undertaker fails to complete the construction of, or part of, the specified works the Canal & River Trust may, if reasonably required in order to avoid detriment, serve on the undertaker a notice in writing requesting that construction be completed. Any notice served under this sub-paragraph shall state the works that are to be completed by the undertaker and lay out a timetable for the works’ completion. If the undertaker fails to comply with this notice within 35 days, the Canal & River Trust may construct any of the specified works, or part of such works (together with any adjoining works) in order to complete the construction of, or part of, the specified works and the undertaker shall reimburse the Canal & River Trust all costs, fees, charges and expenses it has reasonably incurred in carrying out such works.