Paragraph 5 Cooling water pipelines and pumping stationI1
England and Wales
(1)
No part of the authorised development comprising the cooling water pipelines or pumping station may commence until details of the cooling water pipelines and pumping station, including fencing or other means of enclosure, have been submitted to and approved in writing by the relevant planning authority.
(2)
The details approved under sub-paragraph (1) must be in accordance with the following thresholds—
| Number of cooling water pipelines | 2 (one abstraction and one discharge) |
| Maximum diameter | 700 mm (nominal bore) |
| Maximum height of buildings, including security fence | 5 metres |
(3)
The authorised development comprising the cooling water pipelines and pumping station must be implemented in accordance with the approved details.