OpenLegislation

Paragraph 12 Access to work – provision of informationI1

England and Wales

(1)

The undertaker on being given reasonable notice shall—

(a)

at all reasonable times allow reasonable facilities to the engineer for access to a specified work during its construction; and

(b)

supply the engineer with all such information as the engineer may reasonably require with regard to a specified work or the method of constructing it.

(2)

CRT on being given reasonable notice shall—

(a)

at all times afford reasonable facilities to the undertaker and its agents for access to any works carried out by CRT under this Schedule during their construction; and

(b)

supply the undertaker with such information as it may reasonably require with regard to such works or the method of constructing them and the undertaker shall reimburse CRT’s reasonable costs in relation to the supply of such information.

Annotations

Commencement

I1

Sch. 8 para. 12 in force at 1.4.2015, see art. 1

Notes on For the protection of Canal & River Trust

Textual amendments

F1

Words in Sch. 8 sub-heading substituted (23.7.2016) by The Knottingley Power Plant (Correction) Order 2016 (S.I. 2016/797), art. 1, Sch.