Paragraph 14 Maintenance of worksI1

England and Wales

If at any time after the completion of a specified work or a protective work, not being a work vested in CRT, CRT gives notice to the undertaker informing it that the state of maintenance of the work appears to be such that the work is causing or likely to cause detriment, the undertaker shall, on receipt of such notice, take such steps as may be reasonably necessary to put the work in such state of maintenance as not to cause such detriment.

Annotations

Commencement

I1

Sch. 8 para. 14 in force at 1.4.2015, see art. 1

Notes on For the protection of Canal & River Trust

Textual amendments

F1