Paragraph 4 FencingI1
England and Wales
Where so required by the engineer the undertaker shall to the reasonable satisfaction of the engineer fence off a specified work or a protective work or take such other steps as the engineer may require to be taken for the purpose of separating a specified work or a protective work from the waterway, whether on a temporary or permanent basis or both.
Annotations
Commencement
- I1
Sch. 8 para. 4 in force at 1.4.2015, see art. 1
Notes on For the protection of Canal & River Trust
Textual amendments
- F1
Words in Sch. 8 sub-heading substituted (23.7.2016) by The Knottingley Power Plant (Correction) Order 2016 (S.I. 2016/797), art. 1, Sch.