Paragraph 19 I1

England and Wales

(1)

Before beginning to construct any specified work, the undertaker must submit to the Agency plans of the specified work and such further particulars available to it as the Agency may within 28 days of the receipt of the plans reasonably request.

(2)

Any such specified work must not be constructed except in accordance with such plans as may be approved in writing by the Agency or determined under paragraph 30.

(3)

Any approval of the Agency required under this paragraph—

(a)

must not be unreasonably withheld or delayed;

(b)

is deemed to have been refused if it is neither given nor refused within 2 months of the submission of the plans or receipt of further particulars if such particulars have been requested by the Agency for approval; and

(c)

may be given subject to such reasonable requirements as the Agency may have for the protection of any drainage work or the fishery or for the protection of water resources, or for the prevention of flooding or pollution or in the discharge of its environmental and recreational duties.

(4)

The Agency must use its reasonable endeavours to respond to the submission of any plans before the expiration of the period mentioned in sub-paragraph (3)(b).

(5)

Without limiting sub-paragraph (3), the requirements which the Agency may have under that paragraph include conditions requiring the undertaker, at its own expense, to construct such protective works, whether temporary or permanent, before or during the construction of the specified works (including the provision of flood banks, walls or embankments or other new works and the strengthening, repair or renewal of existing banks, walls or embankments) as are reasonably necessary—

(a)

to safeguard any drainage work against damage; or

(b)

to secure that its efficiency for flood defence purposes is not impaired and that the risk of flooding is not otherwise increased,

by reason of any specified work.

(6)

Any specified work, and all protective works required by the Agency under sub-paragraph (4) must be constructed—

(a)

without unreasonable delay in accordance with the plan approved under this Schedule; and

(b)

to the reasonable satisfaction of the Agency,

and the Agency is entitled by its officers to watch and inspect the construction of such works.

(7)

If the Agency reasonably requires, the undertaker must construct all or part of the protective works so that they are in place prior to the construction of any specified work.

Annotations

Commencement

I1

Sch. 13 para. 19 in force at 21.5.2020, see art. 1