Paragraph 13 Piling works risk assessmentI1

England and Wales

(1)

No piling work to be carried out as part of the authorised development may be undertaken until the undertaker has submitted an update to the piling works risk assessment for approval to the Environment Agency.

(2)

Any piling work to be carried out as part of the authorised development must be in undertaken in accordance with the recommendations of the updated piling works risk assessment approved under sub-paragraph (1).

Annotations

Commencement

I1

Sch. 2 para. 13 in force at 21.5.2020, see art. 1