Paragraph 15 Amendment to approved detailsI1

England and Wales

With respect to any requirement which requires the authorised development to be carried out in accordance with the details approved under this Part of this Schedule, the approved details are taken to include any amendments that may subsequently be approved in writing by the body responsible for approving the details for that requirement, following consultation by the undertaker with the Environment Agency, the harbour authority or the local planning authority (where required to do so by the requirement) and the undertaker demonstrating to the body responsible that the amended details would not give rise to any materially new or materially different environmental effects than those assessed in the environmental statement.

Annotations

Commencement

I1

Sch. 2 para. 15 in force at 21.5.2020, see art. 1