Paragraph 1 Directions for additional compensationF1

England and Wales

Changes not yet applied. Later legislation changes this provision in ways not yet written into the text below:

(1)

This paragraph applies if—

(a)

an interest in land has been acquired further to a compulsory purchase order, and

(b)

the order directed that compensation was to be assessed in accordance with section 14A.

(2)

The confirming authority must, on an application by an eligible person, make a direction for additional compensation if it appears to the confirming authority that the following conditions are met.

(3)

Those conditions are—

(a)

that the statement of commitments has not been fulfilled,

(b)

either—

(i)

that the period of 10 years beginning with the date on which the compulsory purchase order became operative has expired, or

(ii)

that there is no longer any realistic prospect of the statement of commitments being fulfilled within that period, and

(c)

that the initial direction would not have been confirmed on the basis of a statement of commitments reflecting what has in fact been done with the project land since its acquisition.

(4)

In sub-paragraph (3)—

  • “the statement of commitments” means the statement of commitments submitted in connection with the compulsory purchase order under section 15A(3) of the Acquisition of Land Act 1981 (and if the statement was amended after its submission, means the statement as amended);

  • “the initial direction” means the direction referred to in sub-paragraph (1)(b) (and that direction was “confirmed” when the compulsory purchase order was confirmed with the inclusion of the direction);

  • “the project land” means the land treated as the project land for the purposes of the statement of commitments;

and that statement is “fulfilled” if what is done with that land after its acquisition is materially in accordance with the statement.

(5)

The effect of a direction for additional compensation is that each eligible person may make a claim to the acquiring authority for any additional compensation in respect of the acquisition payable to the person under this Schedule.

(6)

A person is an “eligible person” for the purposes of this Schedule if the person was entitled to compensation in respect of the acquisition (and see also paragraph 4(1)).

Annotations

Textual amendments

F1

Sch. 2A inserted (31.3.2024 for W. for specified purposes, 30.4.2024 for E.) by Levelling-up and Regeneration Act 2023 (c. 55), ss. 190(2)(c), 255(7) (with s. 247); S.I. 2024/92, reg. 4 (with reg. 6(6)); S.I. 2024/389, reg. 2(l)