Regulation 8 Conditions to be included in landfill permitsI1

Northern Ireland Not yet in force

Changes not yet applied. Later legislation changes this provision in ways not yet written into the text below:

(1)

A landfill permit shall include conditions specifying the list of defined types, and the total quantity, of waste authorised to be deposited in the landfill.

(2)

A landfill permit shall also include appropriate conditions –

(a)

specifying requirements for –

(i)

preparations for, and the carrying out of, landfilling operations;

(ii)

monitoring and control procedures, including contingency plans;

(b)

ensuring that the financial provision required by regulation 4(3)(b)f1 of the 2003 Regulations is maintained until the permit is surrendered in accordance with those Regulations;

(c)

ensuring that the landfill is operated in such a manner that the necessary measures are taken to prevent accidents and to limit their consequences; and

(d)

requiring the operator to report at least annually to the Chief Inspector on –

(i)

the types and quantities of waste disposed of; and

(ii)

the results of the monitoring programme required by regulations 14 and 15.

(3)

A landfill permit shall also include –

(a)

appropriate conditions for ensuring compliance with the requirements of the following provisions of these Regulations –

(i)

Schedule 2 (General requirements for landfills);

(ii)

regulation 9 (Prohibition of acceptance of certain wastes at landfills);

(iii)

regulation 10 (Waste which may be accepted in the different classes of landfill);

(iv)

regulation 11 (Costs of disposal of waste in landfills);

(v)

regulation 12 (Waste acceptance procedures);

(vi)

regulation 13 (Initial site inspections by the Chief Inspector);

(vii)

regulation 14 (Control and monitoring of operational landfills);

(viii)

regulation 15 (Closure and after-care procedures for landfills); and

(b)

such other conditions as appear appropriate to the Chief Inspector, including in particular conditions giving effect to –

(i)

any requirement imposed by Community or national legislation; and

(ii)

in the case of landfills falling within paragraph (a) of Part A of section 5.2 in Part I of Schedule 1 to the 2003 Regulations, the principle that energy should be used efficiently.

(4)

The provisions of these Regulations mentioned in paragraph (3)(a) above shall impose obligations directly on an operator of a landfill (rather than through the conditions of a landfill permit) only to the extent specified in paragraphs 1(14) and 3(3) to (5) of Schedule 4.

Annotations

Commencement

I1

Reg. 8 in operation at 6.1.2004, see reg. 1

Footnotes

f1

See paragraph 1(3) of Schedule 5 to these Regulations