Paragraph 13 Town and Country Planning Act 1990I1

United Kingdom Not yet in force

Changes not yet applied. Later legislation changes this provision in ways not yet written into the text below:

In Schedule 9 (requirements relating to discontinuance of mineral working), in paragraph 1—

(a)

in sub-paragraph (1), for “the development plan and to any other material considerations” substitute “the relevant considerations”;

(b)

after that sub-paragraph insert—

“(1A)

In sub-paragraph (1) “the relevant considerations” are—

(a)

in the case of an authority in England, the development plan, any national development management policies so far as they are material and any other material considerations, or

(b)

in the case of an authority in Wales, the development plan and any other material considerations.”

Annotations

Commencement

I1

Sch. 6 para. 13 not in force at Royal Assent, see s. 255(3)(b)