The Little Crow Solar Park Order 2022f1 (“the Order”), which granted development consent within the meaning of the Planning Act 2008f2 (“the Act”) contains correctable errors within the meaning of paragraph 1 of Schedule 4 to the Act.

In accordance with paragraph 1(5)(a) of Schedule 4 to the Act, and before the end of the relevant period (as defined in paragraph 1(6)(a) of Schedule 4 to the Act), the Secretary of State received a written request from the applicantf3 for the corrections of errors and omissions in the Order.

In accordance with paragraph 1(7) of Schedule 4 to the Act, the Secretary of State has informed the relevant local planning authority for the area in which the land to which the Order relates is situated that the request has been received.

The Secretary of State, in exercise of the powers conferred by sections 119 of, and paragraph 1(4) and 1(8) of Schedule 4 to, the Act, makes the following Order—

Annotations to the whole text

Footnotes

f1

S.I. 2022/436.

f2

2008 c. 29. Paragraph 1 of Schedule 4 was amended by paragraph 70 of Schedule 13, and Part 20 of Schedule 25, to the Localism Act 2011 (c. 20). There are other amendments to paragraph 1 that are not relevant to this Order.

f3

As provided for in paragraph 4 of Schedule 4 to the Act.

Contents

  1. 1Citation and commencement
  2. 2Corrections
  3. Signature
  4. Schedule Correctable Errors
  5. Explanatory note

1Citation and commencement

This Order may be cited as the Little Crow Solar Park (Correction) Order 2023 and comes into force on 10th March 2023.

2Corrections

The Little Crow Solar Park Order 2022 is corrected as set out in the table in the Schedule to this Order, where—

(a)

column 1 sets out where the correction is to be made;

(b)

column 2 sets out how the correction is to be made; and

(c)

column 3 sets out the text to be substituted, inserted or omitted.

Signature

Signed by authority of the Secretary of State for Energy, Security and Net Zero

David Wagstaff

Deputy Director Energy Infrastructure Planning

Department for Energy, Security and Net Zero

9th March 2023

Correctable Errors

ProvisionHow correction is to be madeText to be substituted, inserted or omitted
Schedule 2, Part 1 (requirements)paragraph 8(1)For “outline CEMP” substitute“outline CEMPs”
Schedule 2, Part 1 (requirements) paragraph 8(2), sub-paragraph (h)After the words “investigation or construction” add“and”
Schedule 2, Part 1 (requirements) paragraph 8(2), sub-paragraph (i)After the words “working procedures” omit“and”
Schedule 2, Part 1 (requirements) paragraph 8(2), sub-paragraph (j)Omit“a construction and environmental management plan for biodiversity that must accord with the outline construction and environmental management plan for biodiversity”
Schedule 2, Part 2, paragraph 21(2)(d)For “applicant” substitute“undertaker”
Schedule 2, Part 2, paragraph 21(10)For “applicant” substitute“undertaker”

Explanatory note

(This note is not part of the Order)

This Order corrects errors in the Little Crow Solar Park Order 2022, which granted development consent under the Planning Act 2008, following a request made under paragraph 1(5)(a) of Schedule 4 to that Act.