The Little Crow Solar Park (Correction) Order 2023
S.I. 2023/311 · Made 9 March 2023
Infrastructure Planning
Made 9th March 2023
Coming into force 10th March 2023
In accordance with paragraph 1(5)(a) of Schedule 4 to the Act, and before the end of the relevant period (as defined in paragraph 1(6)(a) of Schedule 4 to the Act), the Secretary of State received a written request from the applicantf3 for the corrections of errors and omissions in the Order.
In accordance with paragraph 1(7) of Schedule 4 to the Act, the Secretary of State has informed the relevant local planning authority for the area in which the land to which the Order relates is situated that the request has been received.
The Secretary of State, in exercise of the powers conferred by sections 119 of, and paragraph 1(4) and 1(8) of Schedule 4 to, the Act, makes the following Order—
Annotations to the whole text
Footnotes
- f1
- f2
-
2008 c. 29. Paragraph 1 of Schedule 4 was amended by paragraph 70 of Schedule 13, and Part 20 of Schedule 25, to the Localism Act 2011 (c. 20). There are other amendments to paragraph 1 that are not relevant to this Order.
- f3
-
As provided for in paragraph 4 of Schedule 4 to the Act.
Contents
1Citation and commencement
This Order may be cited as the Little Crow Solar Park (Correction) Order 2023 and comes into force on 10th March 2023.
2Corrections
The Little Crow Solar Park Order 2022 is corrected as set out in the table in the Schedule to this Order, where—
column 1 sets out where the correction is to be made;
column 2 sets out how the correction is to be made; and
column 3 sets out the text to be substituted, inserted or omitted.
Signature
Signed by authority of the Secretary of State for Energy, Security and Net Zero
David Wagstaff
Deputy Director Energy Infrastructure Planning
Department for Energy, Security and Net Zero
9th March 2023
Correctable Errors
| Provision | How correction is to be made | Text to be substituted, inserted or omitted |
|---|---|---|
| Schedule 2, Part 1 (requirements)paragraph 8(1) | For “outline CEMP” substitute | “outline CEMPs” |
| Schedule 2, Part 1 (requirements) paragraph 8(2), sub-paragraph (h) | After the words “investigation or construction” add | “and” |
| Schedule 2, Part 1 (requirements) paragraph 8(2), sub-paragraph (i) | After the words “working procedures” omit | “and” |
| Schedule 2, Part 1 (requirements) paragraph 8(2), sub-paragraph (j) | Omit | “a construction and environmental management plan for biodiversity that must accord with the outline construction and environmental management plan for biodiversity” |
| Schedule 2, Part 2, paragraph 21(2)(d) | For “applicant” substitute | “undertaker” |
| Schedule 2, Part 2, paragraph 21(10) | For “applicant” substitute | “undertaker” |
Explanatory note
(This note is not part of the Order)
This Order corrects errors in the Little Crow Solar Park Order 2022, which granted development consent under the Planning Act 2008, following a request made under paragraph 1(5)(a) of Schedule 4 to that Act.