Paragraph 3 Expiry of development consentI1
England, Wales and Scotland
(1)
The authorised development must cease generating electricity on a commercial basis no later than the F145th anniversary of the first export date from Work No.1.
(2)
Confirmation of the first export date for Work No.1 must be provided by the undertaker to the local planning authority within one month of its occurrence.
Annotations
Textual amendments
- F1
Words in Sch. 2 para. 3(1) substituted (15.6.2023) by The Little Crow Solar Park (Amendment) Order 2023 (S.I. 2023/660), arts. 1, 3(a)
Commencement
- I1
Sch. 2 para. 3 in force at 27.4.2022, see art. 1